Location No. 43 Ngo Quyen Street, Hanoi, Vietnam Main investor Hanoi Investment and Construction Joint Stock Company Design consulting SF Solutions, Technology and Construction Joint Stock Company Prestressed design and construction Viet Prestressed Concrete Company Limited Construction supervision consulting APAVE Vietnam Company Limited Main contractor Hanoi Investment and Construction Joint Stock Company VIETPT's jobs - Prestressed floor design support
- Floor area: 290 m² per floor
- Supply of materials and installation of 17 tons of prestressing cables for the entire 13-storey building
- Construction schedule: 15 days per floor
- Building span: 11 m. Prestressed floor thickness: 300 mm. Design load: 5 kN/m²
- updating...